Timing Project Manager

The Timing Project Manager (Surface Project Manager or Underground Project Manager) applies to both surface and underground mining for file organization and selection. All files and most settings and configurations used in the mine scheduling are found in the manager. Each topic is described below in detail.

Settings




To use this precedence, turn on the Use Precedence option in the Sequence Window, as seen here and the blocks and panels will reorganize to fit the order.
There are options to set the layer, give it a full description and internal event key name. The Productivity can be set to not working, working (as normal), and not producing (working, but not moving any material). The event delay length is set here by number of shifts. Calendar based will determine if the shift is off in the calendar. If the box is checked, and that shift is off in the calendar already, then it will not take off any more. If it is off, then it will apply to only the next working shift(s) for not working or producing. Additoinal Units can be used to also set other units off during the same period. For example, if a longwall is down due to a move, then the CM working with it can also be down for the same time. There is also an option to Delay Only Additional Units. This can be used to set one unit down, when a different unit crosses the drawing event. This allows for clever equipment delays and precedence by using different drawing events.
 

Equipment

 Calendars

Timing Assignment

The Timing Assignment allows for setting the current sequence. The Assignment is similar to the TIM file in the timing routines. The equipment used and which panels or pits they are mining are shown. The Set Current button controls which one will be loaded and used. Shown here is both a surface mine and an underground mine example.

Panels

This displays the selected underground panels in the mine plan assignment. An example is shown here.

Attribute Groups

Attribute groups are Pit or Panel Attributes assigned to the pits and panels for timing. When timing the pits or panels, there are additional attributes that will be calculated and reported in addition to the Non-Key and Key quantities. If these are defaults that should be applied to all the panels or pits, then they should be entered here. Any quality values, density, or difficulty attributes can be defined here either just as a value, or as a grid file with varying values. The Reserved Attribute Names window displays the reserved words that will be recognized in the timing routines, and how they should be entered in. Selecting Keyword Help brings up the Reserved Attribute Names. If the grid name is red, as shown here, then the file cannot be found. They need to be colored black for successful use.

 

The Reserved Attribute Names are defined in a little more detail here:

Reports

Some of the reports generated in the scheduling will appear here for other options to report. These are also accessed in the calendar or after a schedule is run.

Data Links

This shows the link of the data when it is linked to an external source for reporting.

Pull-Down Menu Location: Reserves/Timing in Surface Mining and Underground in Underground Mining
Keyboard Command:
stime_project or utime_project