Surface Production Timing

This command is used for production based timing of a mineplan to see the mine progress when defining production by time period. It is sometimes referred to a pre-scheduler, prior to running Surface Equipment Timing to get an estimate of mine progression. There are 3 steps needed to prepare for Production Timing as shown in the flow chart below. First, the mining model needs to be set up in the Geologic Model file (PRE). This could also be the geologic model. Next, there must be named, Carlson pit polylines representing the mine plan. Finally, the pits lines must have direction assigned for mining. Once these 3 items are created, the command may be run. This command does not use highwall angles or laybacks. It loads the mining model and vertically intersects it with the directioned pits to obtain timing blocks.

                    Make Geologic Model File ----> Create Named Carlson Pits ----> Assign Directions to Pits ----> Surface Production Timing


The first step is to choose the Geologic Model file to process. After it is selected, the first dialog box appears with some initial settings. The Key Strata Recovery can be entered in the window with Set Value, or can be set By Strata Definitions, where it will refer to the Strata Definition File created with the Define Strata command, or the recovery can be an attribute grid surface found in the geologic model, with the attribute name of REC, which may be customized. The grid would need to contain values from 0-100 for recovery. Each strata can have it's own recovery with the second two options. The Key Strata Density is set in the same way. Either by entering it here, or as defined in the SDF file. The units are either pounds/cubic foot or kg/cubic meter, depending on US units or metric units in the drawing. Finally, the Source of Bottom Surface Model can be set here. If Strata Model is chosen, then the routine will use all seams from the surface topography down to the lowest strata surface in the Geologic Model file. If Surface File is selected, then volumes will only be calculated from the topography down to that bottom surface grid or TIN file, which could be a flat bench elevation for example, or a complex benched pit with many levels. A file-select window will appear next, to choose the grid or TIN if that option is used.

Next, after selecting the pits and the mining project file, the Surface Production Timing window appears as follows.

The first step is to select pits and move them over to the Assignment box on the left with the Assign button. Following is a detailed description of each item in the dialog box.

A finished map with the blocks drawn on it  and the corresponding report are shown here. In this example, the amount was set to 225,000, then 250,000 tons. In the report, notice the accuracy of the tons. Most are within a couple of hundred tons.

Pulldown Menu Location: Surface Mine Module - Reserves/Timing
Keyboard Command: calcplan
Prerequisite: Timing pit polylines