Define Equipment

This command is for inputting and editing the equipment for scheduling routines. It is accessed only in the Timing Project Manager. The productivity of the unit (crew) may vary from shift to shift, up to 4 shifts a day. The number of shifts is set in the Timing window where the sequence of pits or panels is set. The average productivity rate is used for scheduling, however the production rate for the particular pit or panel may be adjusted by setting the difficulty factor or adding delays for that pit or panel. The first window is the edit equipment screen with a columnar display of equipment. Crews can be defined to work with a specific unit, or can switch from unit to unit based on the schedule. Crews are created in the Calendar section of the Timing Project Manager.

Add and Edit will bring up the next screen for detailed entry.

The Unit of the Production value is defined by a rate unit setting. Equipment may mine either tons, tonnes, CY or CM, Distance and Linear Advance. The difference between distance and linear foot of advance settings is that latter one is a combined length of all pathways/entries mined (underground only), and distance is just distance moved, of a longwall for example. 

Enter the Advance Rate/shift or the Advance Rate/hour and the other will be automatically calculated based on the Hours/shift. The Retreat Rate/shift is for Distance and Linear ft of Advance in underground equipment only. The availability value of less than 1.0 will reduce effective production rate of the equipment. 0.94 is a 94% productivity of the full shift.

Underground units may be assigned an Advance minimum and/or maximum height, so that the extra rock will have to be mined or correspondingly unmined coal will be left in the seam if the maximum miner height is less than combined coal and rock parting thicknesses. These settings affect the underground mine timing only.

The maintenance settings provide the ability to schedule a delay for routine or major maintenance/repair of the equipment based on the number of shifts worked. Add in the length of the delay and the number of shifts to determine the frequency.

If operational cost per hour is specified, the total cost will appear in the production report.

The extraction (recovery) factor is used to adjust the amount of material mined form given area to account for certain technical limitations of the equipment such as inability to mine out corners, or not cleaning the top and bottom of ore. This machine will always use that recovery rate.

Advanced Options

Under the Advanced options the variation of equipment-related Difficulty Factor with time, depth or bench number may be specified. Resulting from the advanced options, the difficulty factor is a product of coefficients calculated for given date, thickness and bench number. The final difficulty factor used in calculations is a product of location-specific and equipment-specific difficulty factor.

In the Period End Date column, the difficulty for the date is for next, later date, or last one if no later entry exists. For the thickness column the value of difficulty factor between two entries in the table is a linear approximation. The rehandle value is calculated in the same fashion and passed over to the report, not being used in calculations, but can be used in the report in equations to calculate the total amount mined. The difficulty will modify the rate, and the rehandle is reported. These are not necessarily always the same, linear factors. The Bench Specific Difficulty will be used for surface equipment mining on that bench number, and use that difficulty factor to change the rate of the equipment.

Selecting Edit All from the first screen brings up this editor where all equipment may be viewed and edited. Both the first screen and this one have the import and export buttons.

Pulldown Menu Location: Surface
Keyboard Command: editcrews