Assign Pit Precedence

This command will automatically reassign the precedence for multi-bench pits. If the pits have been edited or cleared of precedence, this command will restore them to the default setting. Bench 2 will always require that Bench 1 gets mined first. Bench 3 will always require that Bench 2 gets mine first and so forth. This is the default setting that should be there, unless the pits have been edited. This will ensure the benches will not under-mine themselves. This command also detects pit overlap and automatically sets precedence accordingly, if the overlap area is greater than the tolerance area.

Prompts

Enter Overlap Area Tolerance (ft^2) <0.0>: Specify the allowed tolerance area
Select pit polylines to process.
Select objects: Specify opposite corner: 3 found
Select objects:
Done.

Pulldown Menu Location: Boundary > Pit Timing Quantities
Keyboard Command: pitprec
Related Command: Edit Pit