Problems Addressed by Natural Regrade with GeoFluv™

Conventional land-shaping practices are often based on conveying or capturing runoff from an extreme event. These conventional practices include grading slopes to a uniform gradient, building gradient terraces across slope faces, and constructing rip-rapped down drains to convey runoff as shown in Figure 1.

Use and Cost Limitations of Conventional Approach
Conventional designs often do not address the hydrologic balance during less extreme flow conditions. This results in problems with reclamation success for vegetation, livestock, and wildlife post-disturbance land uses, high maintenance costs, and reclamation bond complications.

Figure 1. Conventional steep slope reclamation with uniform slope
gradient, gradient terrace, and rip-rap lined downdrain

The unnatural configuration of these designs does not provide the terrain diversity that creates spatial variation in water harvesting and slope aspect. The result is that vegetation tends toward a monoculture and animal habitat is minimized. The native land in the foreground of Figure 1 has forbes and shrubs growing near minor gullies, whereas the uniformly-graded slopes above them do not favor these plants, despite having been seeded with them.  

Conventional land-shaping practices have high construction, maintenance, and liability costs. Terraces can be difficult and expensive to grade on steep side slopes. The rip-rap material may have to be procured off site and transported to the site. After construction, regular maintenance is often required as the terraces and ditches sized for extreme flows become clogged with sediment at lower flows, or are penetrated by burrowing animals. Clogged or burrowed terraces can result in catastrophic diversions of runoff from the terraces straight down the slope, often requiring major repairs.

Bonding Limitations of Conventional Approach
The conventional approach to reclamation landform design affects reclamation bonding liability and costs. The damage to the slope from a blowout and related repair work can result in a reclamation bond clock being restarted, which prolongs the operator’s period of liability. The expense of creating land form designs has often limited an operator’s ability to propose incremental reclamation bonding for various stages of a project’s disturbance. For example, an operator may determine that their greatest disturbance will occur at year four of a five-year permit and they may post a bond for that maximum disturbance, even though their liability will be lower for the first four years. This creates an unnecessary financial burden for the operator.