Connect Mine Plans

Two mine plans which are located in two separate parts of the mine but are sharing the same equipment or just wanted to appear on the same time plan, may be connected into a single mine plan using this command. The only difference between joint mine plan versus conventional one is that mining progresses simultaneously in all connected plans, if equipment use permits that.

The following drawing contains two separate mine plans: Plan A and Plan B.

Plan A panels are shown when the Underground Timing function is selected. (Before connecting)


Panel B panels are shown when the underground timing option is selected and you pick on the Plan B panels.  (Before connecting)

After connecting Plans A & B the list of available panels is composed of both lists.

Pulldown Menu Location: AdvMine
Keyboard Command: connect_plans