Surface Equipment Timing

Surface Equipment Timing schedules through surface pits and blocks based on equipment mining rates in accordance with a calendar. The mining rate is typically based on volume of overburden but may also be based on tons of key strata. The calendar is set by the user to indicate when entire days or individual shifts within a day are down for holidays, time off, or other reasons. The pits themselves must contain key strata and overburden information which is placed in them through use of Surface Reserves, Import Timing Grids, or Assign Timing Data. Surface Equipment Timing is distinct from Surface Production Timing by requiring use of quantities or grids stored in the pits, use of a calendar, and defined rates of production for equipment. The Calendar, Equipment and Crews are defined in the Surface Project Manager.

The Project Manager also appears at the start of Equipment Timing.  The purpose of the timing project database file is to provide a single place where everything related to the timing project is stored. This includes equipment definitions, reporting settings, pit and panel information and reports produced. This also includes other data such as calendars, equipment options, date and weight tables, text block definitions. Basically everything except for the grid files, which will be referenced. This means that reviewing or even repeating results of a schedule done previously will be much easier if everything including the last results is stored in the same place.

The left side of the dialog has a tree control which displays the categories of items on the top level, with either set of items or actual items underneath. Depending on what is selected on the left, the buttons on the right will reflect the functionality available for the current selection. The sets of items showing in bold reflect the current set when applicable: i.e. the project can have multiple sets of equipment defined, but the one showing in bold is one used in calculations. By double-clicking on the item the Edit function can be executed if applicable. For equipment, the user can edit, add, copy or remove entire sets of equipment. Use the Set Current button to set a particular item current. Equipment can be imported from an older Equipment Definition file or from another project. It can also be exported to another file. A number of different data can be output to an external data source or brought up in the report formatter.Following is a detailed description of each function on the Surface Timing window and subsequent windows. After that is a step by step procedure for setting up for the Surface Equipment Timing.


barchart

The program uses the SURFACE grid as a starting elevation and the thickness of each block is relative to the volume of material assigned to each bench in the pits. Benches with more volume will show up thicker than others with less. The color scheme is based on the bench you are on. 
For better viewing of complex pits with separate bench polylines in 3D, surface attribute for each bench can be defined with attribute name SURFACE_BENCH# and value equal to the bench bottom elevation grid. If these attributes are defined the program builds the 3d pick view from top-down calculating the thickness on each pit vertex as elevation difference between two consecutive benches. The red text indicates the grids are moved and cannot be found at that path. There is a reset folder button to address it.
The Schedule Effect on Delay gives two choices: Schedule delay, where the delay will take affect when the equipment is working. If the calendar has the equipment off at that time, then the program waits until it starts to work again, then schedules the delay. A Calendar delay, where if the calendar has it off already, then that is all it will do. It will not take it off additionally. The Due To option provides Drawing Event Types to choose from. Choose the button with "..." next to the Due To, to open the Drawing Event Types window. To Add or Edit a type, the Capture/Timing Event Definition screen provides names and productivity options. Anywhere the text drawn in the Capture Layer is encountered in the drawing, the equipment will be delayed by the Event Delay Length in shifts. The Productivity Effect is the result of the delay. Not working is where the equipment is completely down. Working is no change, and Not Producing is where the equipment is in use, but no quantities are being mined.


A report shows the amount added by unit.

Report Options.
Each item on the dialog box is defined below.

Notes and Comments on Equipment Timing:
Equipment Timing can mimic Surface Production Timing through selection of "Custom Amount Table" at the base of the Report Options dialog. This would be an alternative way of getting to custom table amounts, since the equipment is removed from the equation and is therefore irrelevant. This will target tons of coal, yet report out how many dragline hours need to be scheduled to uncover the coal.

If there are multiple seams (both Key and NonKey) assigned to one bench, the program will report a tonnage and volume factor that applies to each strata. This factor can be used in the User Attributes to calculate the tonnage and volume of each separate strata instead of just a composite number of Key and NonKey.

While Surface Production Timing reports total quantities broken out by seams or specific strata, Surface Equipment Timing only reports totals for all key strata (eg. coal) and overburden, unless Split Report by Strata Fractions is turned on. However, Surface Production Timing does report specific quantities (composited) for each bench. Therefore, a 2-bench mining example will report quantities for Bench 1 (coal C1) and Bench 2 (coal C2). With sufficient benching, the individual strata quantities are retained. For one-bench mining, all multiple strata are composited in the final report.

To practice "what-if" scenarios, use "Undo Report" within the Surface Timing dialog, which will remove the colored hatching, allowing revision of equipment assignments and another practice run.

Prompts
Select all pit polylines.
Select objects:
Pick all polylines

Pull-Down Menu Location: Surface Mining menu, under Surface
Keyboard Command:
timepit
Related Commands:
Surface Mine Reserves, Assign Directions, Surface Project Manager, Assign Timing Grids, Import Timing Data, Define Pit Attributes